In SAP MM and PP, the Scheduling Margin Key's Opening Period allows you to do which of the following ?
(more the one answers)
A) calculate the opening date of a planned order.
B) creating planned orders in the opening period.
C) creating purchase requisition in the opening period.
D) determines the date for the next MRP run.
E) allows the user to have a buffer time to prepare for the purchase order.
.
(more the one answers)
A) calculate the opening date of a planned order.
B) creating planned orders in the opening period.
C) creating purchase requisition in the opening period.
D) determines the date for the next MRP run.
E) allows the user to have a buffer time to prepare for the purchase order.
.