Question no 1101 : Lot Size calculation

In SAP MM PP, Please use the following information to derive the expected MRP calculation results of the Lot Size ?

Current Stocks = 50
No other MRP element exist except the following
      one Sales Order of 200 within the Replenishment Period.
      one Firmed Purchase Requisition of 150 within the Replenishment Period.
      one Reservation of 150 with the Replenishment Period.
Safety Stock is 0
MRP type is Re-Order Point "VB" with ROP at 500
Lot Sizing key is "EX", minimum Lot Size is 40, maximum Lot Size is 200
Rounding Profile of the following
     1 - 99 round to 20
     100 - 599 round to 100
     599 - 9999 round to 500

(only one answer)

A)    4 Planned Orders of 100 each.
B)    A Planned Orders of 380.
C)    3 Planned Orders of 100 each and 1 Planned Order of 80.
D)    A Planned Order of 360.
E)    A Planned Order of 200 and Another Planned Order of 160.
.