In SAP PP and MM, the Goods Receipt Processing Time is ______________ .
(only one answer)
A) setup in the MRP 2 view of the Material Master.
B) setup in the Purchasing view of the Material Master.
C) setup in the Plant/Storage view of the Material Master.
D) setup in the Purchasing Info Record.
E) setup in the Vendor Master Purchasing Organization view.
.