In SAP MM & PP, Please use the following information to derive the expected MRP calculation results of the Lot Size ?
Current Stocks = 0
No other MRP element exist except one Purchase Order of 800 within the Replenishment Period.
Safety Stock is 0
MRP type is Re-Order Point "VB" with ROP at 800
Lot Sizing key is "EX" and minimum lot size is 500
Rounding Value = 12
(only one answer)
A) A Planned Order of 804.
B) A Planned Order of 800.
C) A Planned Order of 800 and Another Planner Order of 4.
D) 42 Planned Orders of 12 each.
E) No Supply MRP Element is created from the Planning Run.
.