In SAP MM & PP, Please use the following information to derive the expected MRP calculation results of the Lot Size ?

Current Stocks = 200
No other MRP element exist for the Material.
Safety Stock is 0
MRP type is Re-Order Point "VB" with ROP at 1000
Lot Sizing key is "EX" and minimum lot size is 200, maximum lot size is 500
Rounding Value = 250

(only one answer)

A)    A Planned Order of 500 and Another Planned Order of 500.
B)    A Planned Order of 250 and Another Planned Order of 500.
C)    A Planned Order of 500 and Another Planner Order of 250.
D)    A Planned Order of 800.
E)    A Planned Order of 300 and Another Planner Order of 500.
.