In SAP PM, when the capacity requirement or capacity load for a work center in a maintenance order released or removed ?
(more then one answers)
A) when a maintenance order is technically completed.
B) when the operation for the work center is set "final confirmation".
C) when the operation for the work center is deleted from the maintenance order.
D) when all the components assigned to the operations of the work center is finally issued.
E) when the maintenance order is set with a "LKD" or locked status.
.
Answer: A, B, C, E