In SAP S/4HANA Quality Management, which of the following QM Processes are NOT TRUE ?

(more than one answers)

A) QM Process cannot be used to set Payment Block to the MM Invoice posted.
B) QM Process can be set to stop MM Invoice Verification creation.
C) QM Process can be set to Block Source Determination.
D) QM Process cannot be set to have Quality Certificate at GR without an Inspection Lot.
E) QM Process can be set to post directly to Unrestricted with an Inspection Lot initially created.
.

Answer: A, B, D

A, B) Until the Inspection Lot is completed, Invoice Verification can be posted but it is Blocked for Payment.
C) In the Quality Info Record, Blocking function for "Source Determination" is possible for combination Vendor, Material, Plant.


D) It is possible to have Quality Certification check at GR without an Inspection Lot.
E) In the Inspection Type detail in the Material Master, the "Post to Inspection Stock" indicator not need be set. If not set, the stock is posted to Unrestricted at Goods Receipt (eg for Inspection Type "01")