In SAP Production Planning & Execution as at S/4 1909, how can the Capacity be possibly reduced in a Production Order ?
(more than one answers)
A) TECO or Technical Completion of the Production Order in CO02.
B) Confirming an Operation using CO11N.
C) Goods Receipt via MIGO with reference to the Production Order.
D) Backflushing the Components of operations using CO11N.
E) Reduce the Production Order quantity in CO02.
.
Answer: A, B, D, E