Case Study: Fixed Bin Storage with MM Quality Inspection for GR (without QM) configuration and process steps. The presentation will show how to setup new Storage Type and Storage Bin for Fixed Bin Storage for a new Spare Parts (Material Master). In addition, the Material Spare Parts will required GR into Inspection Stock (but without QM Module). Then setup Direct QI Stock Category to Unrestricted Stock Transfer within WM.

Click this link to see the Presentation "QI to UR without QM".

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Case Study: Storage Location MRP replenishment from Main Store to Storage Location. Using Special Procurement Key "45" to initiate STPR (then STPO) to transfer from Issuing SLoc to Receiving SLoc within the SAME Plant.

CLICK this link to see the Presentation "MRP run for Replenishment via STPR then STPO from SLoc to SLoc"

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Case Study: Backlashing Spare Parts stocks for Maintenance Order. The presentation shows how to setup Spare Parts for Backflushing at Maintenance Order Confirmation.

Click this link to see the Presentation "Spare Parts Backflushing at Maintenance Order Confirmation"

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Case Study: MRP Area (Storage Location) replenishment from Plant to MRP Area. Setup Storage Location as MRP Area and use Special Procurement key "45" and via MRP run to create Transfer Reservation from Plant level to the MRP Area.

Click this link to see the Presentation "SAP MM - SLoc to SLoc Replenishment for MRP Area within the same Plant"

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------