In SAP QM ECC6.0 EhP6, Study the graphics, what can happen to the material when goods receipt was performed ?


(more than one answers) 

A)   Stock was posted to un-restricted. 
B)   You cannot save this setting in the Material Master. 
C)   No Inspection Lot created.
D)   Inspection Lot created with 'REL' status.
E)   Inspection Lot created with 'UD' status.
.

1 comment:

  1. Inspection Lot will be created with 'REL' status waiting for UD (without RR), Stocks will be immediately in 'Un-restricted' stock status. Usage Decision will have no impact to the stock status.