In SAP QM ECC6.0 EhP6, which of the following scenario combinations of Inspection processing are possible ?
(more than one answers)
A) Only Material Specifications for a Material.
B) Only Inspection Plan for a Material.
C) Both Material Specification and Inspection Plan for a Material.
D) Without Material Specification and Without Inspection Plan for a Material.
E) All of the above.
.
(more than one answers)
A) Only Material Specifications for a Material.
B) Only Inspection Plan for a Material.
C) Both Material Specification and Inspection Plan for a Material.
D) Without Material Specification and Without Inspection Plan for a Material.
E) All of the above.
.
Answer: A, B, C, D, E
ReplyDeleteThese combination setting is available for each material at the plant level for each inspection type in the QM data view. All combinations are possible.
ReplyDeleteIn the case of both Material Specification and Inspection Plan. The system will read both into the Inspection Lot except if there are duplicating Inspection Characteristics in both, the system ignores it when copying the Material Specification inspection characteristics to the Inspection Lot.