This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Tuesday, March 10, 2015

Question no 2735 : Material Specification and Inspection Plan

In SAP QM ECC6.0 EhP6, which of the following are available in the Inspection Plan but not in the Material Specification ?

(more than one answers)

A)   Task List Usage.
B)   Inspection Point.
C)   Sampling Procedure.
D)   Work Center.
E)   Plant.
.

2 comments:

  1. The Inspection Plan has a Task list header where the Material Specification does not have a Header. In this case, it is simple to note that the Inspection Plan Header's data is not available with the Material Specification namely:
    . Task List Usage (which is important for differentiating Inspection Plans for different Inspection Types)
    . Inspection Point (which is required for example In-process Inspection and Physical Sample procedures)
    . Sample Drawing Procedure (for Physical sample drawing instruction)
    . Dynamic Modification Rule (for managing Quality Level stage changes)

    In the Operation level, the Inspection Plan has the following where the Material Specification is lack of:
    . Work Center
    . Inspection Hours
    . Control Key

    At the most basic level, no Engineering Change application is available for Material Specification yet as at ECC6.0 EhP6.

    ReplyDelete

Note: Only a member of this blog may post a comment.