In SAP QM ECC6.0 EhP6, which of the following are available in the Inspection Plan but not in the Material Specification ?
(more than one answers)
A) Task List Usage.
B) Inspection Point.
C) Sampling Procedure.
D) Work Center.
E) Plant.
.
(more than one answers)
A) Task List Usage.
B) Inspection Point.
C) Sampling Procedure.
D) Work Center.
E) Plant.
.
Answer: A, B, D, E
ReplyDeleteThe Inspection Plan has a Task list header where the Material Specification does not have a Header. In this case, it is simple to note that the Inspection Plan Header's data is not available with the Material Specification namely:
ReplyDelete. Task List Usage (which is important for differentiating Inspection Plans for different Inspection Types)
. Inspection Point (which is required for example In-process Inspection and Physical Sample procedures)
. Sample Drawing Procedure (for Physical sample drawing instruction)
. Dynamic Modification Rule (for managing Quality Level stage changes)
In the Operation level, the Inspection Plan has the following where the Material Specification is lack of:
. Work Center
. Inspection Hours
. Control Key
At the most basic level, no Engineering Change application is available for Material Specification yet as at ECC6.0 EhP6.