In SAP QM as at ECC6.0 EhP6, in order for an inspection lot to be able to perform calibration for multiple equipments, the system has to generate inspection requirements for every equipment with 'containers' within one inspection lot, how can that be possible ?
(only one answer)
A) Inspection Point assigned to the Inspection Plan Header.
B) Inspection Point assigned to the Equipment Category.
C) No setup required, this is built-in capability in the Maintenance Plan functionality.
D) Inspection Point assigned to the Maintenance Task List.
E) This is not possible, one inspection lot can only perform calibration for one equipment.
.
(only one answer)
A) Inspection Point assigned to the Inspection Plan Header.
B) Inspection Point assigned to the Equipment Category.
C) No setup required, this is built-in capability in the Maintenance Plan functionality.
D) Inspection Point assigned to the Maintenance Task List.
E) This is not possible, one inspection lot can only perform calibration for one equipment.
.
If you carry out calibration inspections and want to record inspection results for equipment or functional locations, choose the inspection point type for Equipment or Functional location. You can create your own field combinations for these inspection types in Customizing. However, the field Equipment or Functional location must exist in the field combination.
ReplyDeleteThe Inspection Point is assigned to the header of a Task List. (in this case the Maintenance Task List)