This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Friday, March 6, 2015

Question no 2680 : Collective or Individual documents in the Maintenance Order

In SAP PM as at ECC6.0 EhP6, the maintenance manager request the following possibilities for the maintenance order processing, which of the following cannot be done ?

A)   Collective Purchase Requisition for each maintenance order.
B)   Individual Purchase Requisitions for all external procurement within each maintenance order.
C)   Collective Reservation for each maintenance order.
D)   Individual Reservations for every stock item within each maintenance order.
E)   Individual confirmation number for each operation in the maintenance order.
.

4 comments:

  1. A, B) Individual or Collective PR for external requirements within a Maintenance Order can be configured at IMG - PM/CS - Maintenance & Service Processing - Maintenance and Service Orders - Functions and Settings for Order Types - Define Change Document, Collective PR, MRP Relevance

    ReplyDelete
  2. C, D) As at ECC6.0 EhP6, individual or collective Reservations is not configurable. SAP delivery is 1 reservation (collective reservation) for each Maintenance Order.

    ReplyDelete
  3. E) Standard SAP delivery is each operation one confirmation number, not configurable for one single or collective confirmation number for all operations in one maintenance order. (as at ECC6 EhP6)

    ReplyDelete

Note: Only a member of this blog may post a comment.