Question no 2678 : Maintenance Task List

In SAP PM as at ECC6 EhP6, what are the correct relationships of General Maintenance Task List to different objects in PM ?

(mire than one answers)

A)  Only one General Maintenance Task List can be assigned to each Maintenance Notification.
B)  More than one General Maintenance Task List can be assigned to each Maintenance Order.
C)  Each Maintenance Plan Item can have exactly one General Maintenance Task List.
D)  In the General Maintenance Task List Master header, you can assign one or more Equipment.
E)  it is not possible assign a General Task List to a Maintenance Notification.

4 comments:

  1. A, E) Configuration of the Notification Type with a 'Maintenance Plan' screen TAB will allow you to enter exactly one General Task List to each Maintenance Notification.

    ReplyDelete
  2. B) Standard SAP does allow you to include one more General Maintenance Task List to each Maintenance Order, you ca. Perform this manually in the Order itself. However, when you have several Maintenance Notifications each assigned with General Task List and there are converted to ONE Maintenance Order, all the General Task List are autimatically included in the Order.

    ReplyDelete
  3. C) Each Maintrnance Item can have exactly one General Maintenance Task List. However this is only applicable for Single Cycle Plans, Strategy Plan, and Multi-Counter Plans.