In SAP PM, the Estimated Cost of maintenance in the maintenance order contains the following characteristics.
(more then one answers)
A) It can only be entered before the maintenance order released.
B) It can only be entered before the maintenance order is technically completed.
C) Only values can be entered and not quantities.
D) Both quantities and values can be entered.
E) The estimated costs will be used as Maintenance Budget control and checking.
.
(more then one answers)
A) It can only be entered before the maintenance order released.
B) It can only be entered before the maintenance order is technically completed.
C) Only values can be entered and not quantities.
D) Both quantities and values can be entered.
E) The estimated costs will be used as Maintenance Budget control and checking.
.
Answer: A, C
ReplyDeleteEstimated costs are for information and comparison only and can only be entered as values in value categories.