In SAP PM, use the following data the Capacity Header of the Work Center to derive the additional number of technician required if the Available capacity is to increase to 36 hours.
Start time : 07:00:00
Finish time : 17:00:00
Length of breaks : 01:00:00
Capacity Utilization : 100%
No. of individual capacity : 3
(only one answer)
A) 1
B) 2
C) 3
D) 4
E) 5
.
Answer: A