In SAP PM, use the following data the Capacity Header of the Work Center to derive the Available Capacity.
Start time : 07:00:00
Finish time : 17:00:00
Length of breaks : 01:00:00
Capacity Utilization : 90%
No. of capacity utilization : 3
(only one answer)
A) 24.00
B) 25.00
C) 24.30
D) 27.00
E) 30.00
.
Answer: C