Question no 1456 : Available Capacity Calculation

In SAP PM, use the following data the Capacity Header of the Work Center to derive the Available Capacity.

Start time : 07:00:00
Finish time : 17:00:00
Length of breaks : 01:00:00
Capacity Utilization : 90%
No. of capacity utilization : 3

(only one answer)

A)    24.00
B)    25.00
C)    24.30
D)    27.00
E)    30.00
.