In SAP PP, a Production order ____________________ .

(more then one answers)

A)    Cannot be created for without a material master.
B)    Must have a minimum of one operation.
C)    Can be created without a BOM.
D)    Must have a minimum of one component.
E)    Cannot be released until a BOM and Routing is entered.
.

2 comments:

  1. Even there is no Routing, the Production Order will be created with one operation. However, when a BOM is not found, the Production Order can proceed without any components.