Question: What is PPAP (Production Parts Approval) in SAP?


Answer: Production Part Approval Process (PPAP) includes a set of standard processes that ensures the production process of a material meets your requirements. 
  • An essential part is the first article inspection (FAI).
  • You enable PPAP in the Manage Quality Info Records app. There you can specify for a material that a first article inspection should take place at goods receipt for one or several purchase order items.
See the following Presentation:
https://docs.google.com/presentation/d/1M7UmZZgfau_rFRWo7jJx0_uR8yYSQSKeUF5IESVNta8/edit?usp=sharing

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Question: S/4HANA RR and UD using FIORI App.


Answer: See the following Presentation:
https://docs.google.com/presentation/d/1OfztDazkHpRgv-Wc0BBzXdy0KuInDWjW4qmAzzK2Axg/edit?usp=sharing

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Question: How is 8D Methodology implemented in SAP S/4HANA?


Answer: In SAP S/4HANA, 8D problem-solving is a structured methodology used to identify, correct, and eliminate recurring quality issues. It provides a systematic approach to problem-solving, guiding users through eight distinct phases. This approach is particularly helpful in identifying root causes, implementing interim fixes, and developing permanent solutions to prevent future recurrences. 
Here's a breakdown of the 8D methodology in SAP S/4HANA:
  1. 1. D0: Plan: This initial phase involves planning the problem-solving process, including defining the scope, setting objectives, and identifying resources. 
  2. 2. D1: Use a Team: A cross-functional team is formed, bringing together individuals with relevant expertise to collaborate on the problem. 
  3. 3. D2: Define and Describe the Problem: The problem is clearly defined, specifying the who, what, where, when, and how of the issue. 
  4. 4. D3: Develop Interim Containment Plan: Temporary measures are implemented to contain the problem and prevent further damage. 
  5. 5. D4: Identify and Verify Root Causes: The team investigates the underlying causes of the problem using various root cause analysis techniques. 
  6. 6. D5: Develop and Implement Corrective Actions: Permanent solutions are designed and implemented to address the identified root causes. 
  7. 7. D6: Verify Corrective Actions: The effectiveness of the implemented solutions is verified to ensure that the problem has been resolved. 
  8. 8. D7: Prevent Recurrence: Preventive actions are put in place to avoid future recurrences of the problem. 
  9. 9. D8: Recognize the Team: The team is recognized for their efforts and the successful resolution of the problem.