Question no 3907 : IH01 display objects in Structure format
In SAP PM as at ECC6.0 EhP6, which of the following can be displayed as hierarchy structure in IH01 ?
(more than one answers)
A) Permits.
B) Classification data.
C) Equipment Hierarchy.
D) Construction Type.
E) Work Center Hierarchy.
.
Answers: A, C, D
(more than one answers)
A) Permits.
B) Classification data.
C) Equipment Hierarchy.
D) Construction Type.
E) Work Center Hierarchy.
.
Answers: A, C, D
The following can be displayed as part of the hierarchy:
(selectable from the initial screen of IH01)
Functional Location Hierarchy
Equipment installed
Equipment Hierarchy
Expand Construction Type
BOM Explosion
Explosion of IBase
PermitsDeleted Objects
Monday, December 27, 2021
Question no 3906 : LAM in Functional Location
In SAP PM as at ECC6.0 EhP6, which of the following precisely provides the additional data views of LAM data in a Functional Location ?
(only one answer)
A) View Profile assigned to the Functional Location Category.
B) Functional Location Category Field Selection.
C) Combination of Functional Location Category and Edit Mask.
D) Planning Plant Parameter for Planning Plant assigned to the Functional Location Master.
E) User Profile.
.
Answer: A
Both EQ and FL Category are assigned with View Profiles for different types of TABS and data views of each TAB.
(only one answer)
A) View Profile assigned to the Functional Location Category.
B) Functional Location Category Field Selection.
C) Combination of Functional Location Category and Edit Mask.
D) Planning Plant Parameter for Planning Plant assigned to the Functional Location Master.
E) User Profile.
.
Answer: A
Both EQ and FL Category are assigned with View Profiles for different types of TABS and data views of each TAB.
IMG - PM & CS - Master Data in PM & CS - Basic Settings - Technical Objects - General Data - Set View Profiles for Technical Objects.
In this configuration, create a View Profile ID with the desired Screen Group for either Equipment or Functional Location and then create the TABs views with screen numbers.
next
Assign the view Profile to the Equipment Category or Functional Location Category in the following:
IMG - PM & CS - Master Data in PM & CS - Basic Settings - Technical Objects - Equipment - Equipment Category - Maintain Equipment Category.
IMG - PM & CS - Master Data in PM & CS - Basic Settings - Technical Objects - Functional Locations - Functional Location Category.
Saturday, December 25, 2021
Wednesday, December 22, 2021
Question no 3905 : MRP Run
In SAP MM/PP as at ECC6.0 EhP6, which of the following are possible choice of MRP Run ?
(More than one answers)
A) MRP Run for multiple plants.
B) MRP Run for one single Material.
C) MRP Run for selected Materials.
D) MRP Run Interactively.
E) MRP Run for a Storage Location.
.
Answers: A, B, C, D, E
A) Via Scope of Plan in MD01 or MDBT.
(More than one answers)
A) MRP Run for multiple plants.
B) MRP Run for one single Material.
C) MRP Run for selected Materials.
D) MRP Run Interactively.
E) MRP Run for a Storage Location.
.
Answers: A, B, C, D, E
A) Via Scope of Plan in MD01 or MDBT.
(note that in S4, Multi-Plant Planning is possible via MD01N or MRP Live because SAP included multiple entries for the Plant field (no more Scope of Plan field)
B) MD03 Single item Single level MRP run.
C) Via User Exit in MD01 or MDBT.
B) MD03 Single item Single level MRP run.
C) Via User Exit in MD01 or MDBT.
(note that in S4, MD01N or MRP Live allows multiple fields or "range" entry for not just Material field, but also Plant, MRP Controller, and Product Group).
D) MD43 runs MRP interactively (this means, MD43 first shows the current situation of demand-supply in MD04 and user can decide to perform Multi-level MRP run for that Material and review the MRP results before Saving or Exit without Saving).
E) Run MRP via MRP Area. (where Storage Location is assigned to MRP Areas which can be found in MD02).
D) MD43 runs MRP interactively (this means, MD43 first shows the current situation of demand-supply in MD04 and user can decide to perform Multi-level MRP run for that Material and review the MRP results before Saving or Exit without Saving).
E) Run MRP via MRP Area. (where Storage Location is assigned to MRP Areas which can be found in MD02).
Monday, December 20, 2021
Question no 3904 : A Planned Order
In SAP MM/PP as at ECC6.0 EhP6, which of the following are TRUE about Planned Orders ?
(more than one answers)
A) A Planned Order can be created manually.
B) Planned Orders can be deleted by the user.
C) Planned Orders can be firmed automatically.
D) Planned Orders can be firmed manually.
E) A Planned Order can be generated by MRP run.
.
Answers: A, B, C, D, E
A) You can use transaction code MD11 to create Planned Orders manually.
(more than one answers)
A) A Planned Order can be created manually.
B) Planned Orders can be deleted by the user.
C) Planned Orders can be firmed automatically.
D) Planned Orders can be firmed manually.
E) A Planned Order can be generated by MRP run.
.
Answers: A, B, C, D, E
A) You can use transaction code MD11 to create Planned Orders manually.
B) Via MD12 or Change MRP Element in MD04, the Planned Orders can be deleted.
C) Using Time Fence, either manual setup in MD04 or via appropriate MRP Type with Firming indicator plus the MRP1 view Time Fence; Planned Orders can be firmed automatically.
D) Via MD12 or Change MRP Element in MD04, the Planned Orders can be Firmed manually.
E) For External Procurement, the setting "Create PR" and "Create Scheduling" indicators in MD01, MDBT, MD02 allows to control creation of Planned Orders. However, for Internal Procurement, Planned Orders are always created if necessary as MRP run cannot create Production Orders.
Thursday, December 16, 2021
Wednesday, December 15, 2021
Question no 3903 : MRP run Master Data
In SAP MM/PP as at ECC6.0 EhP6, which of the following is not used in an MRP run when it creates a Planned Order ?
(Only one answer)
A) Quota Arrangement.
B) Source List.
C) Stock Determination Rule.
D) Scheduling Margin Key.
E) Lot Size Key.
.
Answer: C
A) Quota Arrangement is activated when MRP usage for Quota Arrangement is activated in the MRP 2 data view (in ECC6), but this indicator is not longer available is S4 meaning there is no Material Master activation required in S4 for usage of Quota Arrangement in S4.
(Only one answer)
A) Quota Arrangement.
B) Source List.
C) Stock Determination Rule.
D) Scheduling Margin Key.
E) Lot Size Key.
.
Answer: C
A) Quota Arrangement is activated when MRP usage for Quota Arrangement is activated in the MRP 2 data view (in ECC6), but this indicator is not longer available is S4 meaning there is no Material Master activation required in S4 for usage of Quota Arrangement in S4.
B) Source List can be set with MRP relevancy for each source so that MRP run will use the information to Supply creation.
C) Stock Determination Rule is used for Storage Location determination for Reservations or Orders in MIGO, and not relevant at point of MRP run for Supply determination.
C) Stock Determination Rule is used for Storage Location determination for Reservations or Orders in MIGO, and not relevant at point of MRP run for Supply determination.
D) Scheduling Margin Key set in MRP2 view is mandatory setting when a valid MRP type is assigned to the Material, the Opening Period from the SMK is used to determine the Planned Orders Opening date. It can also be used to create Planned Orders in the Opening Period.
E) The Lot Size Key set in MRP1 view is used to determine the Lot Size used to create the Planned Orders in an MRP run.
Monday, December 13, 2021
Question no 3902 : Quota Arrangement with Split Quantities
In SAP MM/PP as at ECC6.0 EhP6, which of the following field allows the MRP calculated quantity to split between the sources in the Quota Arrangement based on its Ratios ?
(only one answer)
A) MRP Type.
B) Lot Size Key.
C) Procurement Type.
D) Special Procurement Key.
E) Scheduling Margin Key.
.
Answer: B
SAP Lot Size key "ES" is configured with the "Split" indicator for this purpose. The "Split" indicator in the Lot Size parameter is the key that enables the split.
(only one answer)
A) MRP Type.
B) Lot Size Key.
C) Procurement Type.
D) Special Procurement Key.
E) Scheduling Margin Key.
.
Answer: B
SAP Lot Size key "ES" is configured with the "Split" indicator for this purpose. The "Split" indicator in the Lot Size parameter is the key that enables the split.
Wednesday, December 8, 2021
Question no 3901 : Planned Orders conversion
In SAP MM/PP MRP as at ECC6.0 EhP6, the push buttons available in the dialogue box of a Planned Order MRP Element is controlled by which of the following ?
(only one answer)
A) MRP Type.
B) MRP Group.
C) Procurement Type.
D) Scheduling Margin Key.
E) Plant Parameter.
.
Answer: C
The Procurement Type X, E, or F determines the push button that will be available in the dialogue box of a Planned Order MRP Element.
(only one answer)
A) MRP Type.
B) MRP Group.
C) Procurement Type.
D) Scheduling Margin Key.
E) Plant Parameter.
.
Answer: C
The Procurement Type X, E, or F determines the push button that will be available in the dialogue box of a Planned Order MRP Element.
The Material Type configuration decides the Material Master MRP2 view Procurement type field definition which will affect the Planned Order conversion possibilities.
Monday, December 6, 2021
Question no 3900 : Stock Requirement List
In SAP MM/PP as at ECC6.0 EhP6, which of the following is not an MRP Element in a Stock Requirement List ?
(more than one answers)
A) RFQ.
B) Contract.
C) Repetitive Planned Order.
D) Production Order.
E) Sales Order.
.
Answers: A, B
Not RFQ nor Contract.
(more than one answers)
A) RFQ.
B) Contract.
C) Repetitive Planned Order.
D) Production Order.
E) Sales Order.
.
Answers: A, B
Not RFQ nor Contract.
Wednesday, December 1, 2021
Question no 3899 : MRP Run using MD01
In SAP MM/PP as at ECC6.0 EhP6, which of the following features are Correctly described in MRP run via MD01 ?
(more than one answers)
A) Scope of Plan is used to exclude a list of Materials from an MRP run.
B) Plant and MRP Area can be sequenced using the Scope of Plan.
C) Regenerative MRP run can be executed in MD01.
D) User Exit Key allows you to filter Materials in the MRP run.
E) Work Center Capacity version can be changed for an MRP run.
.
Answers: B, C, D
A, B) Scope of Plan is to sequence Plant and/or MRP area.
C) Regenerative, Net Change, and Net Change within Planning Horizon possible in MD01.
D) User Exit Key can be used for Material filtering in an MRP run.
E) You can switch Capacity version in Long Term Planning Scenario.
(more than one answers)
A) Scope of Plan is used to exclude a list of Materials from an MRP run.
B) Plant and MRP Area can be sequenced using the Scope of Plan.
C) Regenerative MRP run can be executed in MD01.
D) User Exit Key allows you to filter Materials in the MRP run.
E) Work Center Capacity version can be changed for an MRP run.
.
Answers: B, C, D
A, B) Scope of Plan is to sequence Plant and/or MRP area.
C) Regenerative, Net Change, and Net Change within Planning Horizon possible in MD01.
D) User Exit Key can be used for Material filtering in an MRP run.
E) You can switch Capacity version in Long Term Planning Scenario.