In SAP PP, which of the following statements are TRUE ?
I) A BOM is required when creating a production order.
II) At least one operation is needed when creating a production order.
III) A production order can be created without a material.
IV) A production order can be created when saving a Sales Order.
A) I, II
B) II only
C) II, III
D) I, II, III
E) I, II, III, IV
.
This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes
Saturday, December 12, 2009
Thursday, December 10, 2009
Question no : 237 PP MRP Mechanics
In SAP PP, "NETCH" is:
A) Net Change in total horizon.
B) Nat Change within planning horizon.
C) Regenerative.
D) Planning Strategy.
E) Not related to MRP.
.
Tuesday, December 8, 2009
Question no : 236 PP MRP Mechanics
In SAP PP, with Make-to-Stock strategy "11", the MRP calculations considers:
I) Stocks.
II) Sales Orders.
III) Planned Independent Requirements.
IV) Sales Orders Consumes the PIR.
V) Existing Production Orders.
A) I, III, V
B) III
C) III, V
D) I, III, V
E) I, II, III, IV, V
.
I) Stocks.
II) Sales Orders.
III) Planned Independent Requirements.
IV) Sales Orders Consumes the PIR.
V) Existing Production Orders.
A) I, III, V
B) III
C) III, V
D) I, III, V
E) I, II, III, IV, V
.
Sunday, December 6, 2009
Question no : 235 PP MRP Planning concepts
In SAP MM/PP, MRP can be set to automatically create which of the following MRP element ?
I) Purchase Requisition.
II) Purchase Order.
III) Production Order.
IV) Delivery schedule for Scheduling Agreement.
V) Delivery schedule for Sales Order.
A) I, II, IV
B) I, IV, V
C) I, II, III, IV
D) I, IV
E) I, II, III, IV, V
.
I) Purchase Requisition.
II) Purchase Order.
III) Production Order.
IV) Delivery schedule for Scheduling Agreement.
V) Delivery schedule for Sales Order.
A) I, II, IV
B) I, IV, V
C) I, II, III, IV
D) I, IV
E) I, II, III, IV, V
.
Friday, December 4, 2009
Question no : 234 PP MRP Stock Requirement List
In SAP MM for MRP, which of the following can be viewed as an MRP element in the Stocks Requirements List ?
I) Quotation.
II) RFQ.
III) Contract.
IV) Purchase Requisition.
V) Quota Arrangement.
A) I, IV.
B) I, III, IV.
C) III, IV.
D) IV, V.
E) IV.
.
I) Quotation.
II) RFQ.
III) Contract.
IV) Purchase Requisition.
V) Quota Arrangement.
A) I, IV.
B) I, III, IV.
C) III, IV.
D) IV, V.
E) IV.
.
Wednesday, December 2, 2009
Question no : 233 PP MRP Evaluation
In SAP MM, You can view the most updated planning and execution data (such as Purchase Requisition, Purchase Order), which of the following transaction would be most suitable:
A) MRP List.
B) Stock Requirement List.
C) Standard Analysis for Material List.
D) Stock Overview.
E) Material Document list.
.
A) MRP List.
B) Stock Requirement List.
C) Standard Analysis for Material List.
D) Stock Overview.
E) Material Document list.
.
Subscribe to: