Question no 3974 : Leading and Dependent Orders in Manufacturing
(only one answer)
A. Multi-level Production.
B. Joint Production.
C. Collective Orders.
D. Production Version.
E. Special Procurement Key.
Answer: C
Collective orders can consist of planned orders or manufacturing orders (production orders or process orders).
A collective order consists of the following:
A leading order
The leading order is the order at the highest level of the collective order. It is created to manufacture the finished product.
Dependent orders
All orders below the leading order are dependent orders. The system automatically creates the dependent orders for the leading order. Dependent orders can be subordinate to each other on multiple levels of the collective order.
Changes to higher-level orders (such as a changed order quantity or release of the order) are immediately reflected in all dependent orders when the order is saved.
Wednesday, July 12, 2023
Sunday, July 9, 2023
Saturday, July 8, 2023
Friday, July 7, 2023
Q&A in Class (2023-07-07) S4225
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Negative Stock Setup in S/4- Ensure all staged materials are transferred to the shop floor in standard packing.
- Any defects of the components must be reported.
- Extra (additional) component quantities must be segregated or return to the warehouse.
- Ensure staged materials stock counting frequently to ensure reasons for inaccuracies are treated on time.
- Shop floor stocks should be under the responsibility of the production department.
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Overhead calculation with Origin and OH Group + OH Key with Material and labor from Production order creation to settlement up to CLSD
Refer to the following Blog Posts:
https://froggysap.blogspot.com/2022/12/sap-fico-costing-sheet-with-different.html
https://froggysap.blogspot.com/2016/05/ppdi-costing-final-settlement-for.html
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
How to setup background via a standard SAP transaction for a Program
Background job is setup as a non-interactive process that runs behind the normal interactive operations at specific intervals. Whether it is ECC or S/4, Background Jobs are scheduled using transaction code SM36 and usually this is done by the Basis Consultant (or Netweaver/BTP Consultant). Users can then analyze the Background Jobs via transaction code SM37 by viewing its job log.
S/4 Hana backend continues to make available t-codes SM36 and SM37 for Background Job creation or Monitoring. However, S/4 Hana Fiori App in specific modules provide a "user-friendly" method of creating Background Jobs. see the example of how Background Jobs are created using S/4 Backend and S/4 Fiori App on the Blog Post link below:
https://froggysap.blogspot.com/2023/07/blog-post.html
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Batch for FG that show the raw material origin for SD delivery auto batch determination with Quality Certificate for raw material batch origin
To demonstrate the batch determination in SD Outbound Delivery for customer that require material origin from specific countries.
The Product is Y_FG1 with Component Y_RM1
Y_RM1 batches OriginBatch A Japan
Batch C China
Batch D Thailand
Y_FG1 batches Raw Material Batch used for the Finished Goods
F1 Batch A from Japan
F2 Batch D from Thailand
F3 Batch A from Japan
F4 Batch B from Korea
F5 Batch C from China
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Tuesday, July 4, 2023
Saturday, July 1, 2023
Question no 3973 : In-Complete Procedure assignment in Sales Order Processing
(more than one answers)
A. Sales Document's Document Type.
B. Item Category.
C. Requirement Type.
D. Item Category Group.
E. Sales Area.
.
Answer: A, B
The SD In-completion Procedure can be assigned to the following:
- Sales Document Type
- Item Category
- Schedule Line Categories
- Partner Functions
- Delivery Types
- Delivery Item Categories