This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Monday, November 30, 2020

Question no 3767 : MRKO

In SAP MM as at ECC6.0 EhP6, which of the following are possible via T-code MRKO ?

(more than one answers)

A)  Pipeline settlement.
B)  Invoicing Plan settlement.
C)  ERS settlement.
D)  Gr-Based IV settlement.
E)  Consignment settlement.
.

click "1 comment" t o view suggested solution

Wednesday, November 25, 2020

Question no 3766 : Auto Release Blocked Invoices

In SAP MM as at ECC6.0 EhP6, which of the following Invoicing Blocking reasons can be removed/release automatically via t-code MRBR ?

(more than one answers)

A)  Quantity Block.
B)  Date Block. 
C)  Stochastic Block.
D)  Item Amount Block.
E)  Manual Block.
.

click "1 comment" to view suggested solution.

Tuesday, November 24, 2020

Question no 3765 : Invoice without PO Reference

In SAP MM as at ECC6.0 EhP6, which of the following are the possible when performing Invoice Verification without PO reference ?

(more than one answers)

A)  Post directly to a selected G/L Account.
B)  Post directly to a Material Master Stock Account.
C)  Post directly to a Equipment Master.
D)  Post directly to a Material Document.
E)  Post directly to a Contract.
.


click "1 comment" to view suggested solution.

Monday, November 23, 2020

Question no 3764 : Invoice Header Block

In SAP MM as at ECC6.0 EhP6, which of the following Invoice Block is at the Header level ?

(only one answer)

A)  Quantity variance Block.
B)  Item Amount Block.
C)  Order Price Quantity variance Block.
D)  Price variance Block.
E)  Stochastic Block.
.

click "1 comment" for suggested solution

Wednesday, November 18, 2020

Question no 3763 : Inspection Plan characteristics

In SAP QM as at ECC6.0 EhP6, which of the following are the characteristics of an Inspection Plan ?

(more than one answers)

A)  An Inspection Plan can be assigned to one of more Plants.
B)  An Inspection Plan can be assigned to one or more Materials.
C)  An Inspection Plan can have one or more Counters.
D)  An Inspection Plan can be created without a Plant.
E)  An Inspection Plan can be assigned to one or more Equipment..
.

click "1 comment" to view suggested solution

Tuesday, November 17, 2020

Question no 3762 : Call Object Inspection Lot

In SAP QM as at ECC6.0 EhP7, which of the following scenario of using Maintenance Plan where the Call Object is an Inspection Lot in Standard SAP ?

(only one answer)

A)  Calibration.
B)  Refurbishment.
C)  Asset Under Construction.
D)  Corrective.
E)  Stability Study.
.

click "1 comment" to view suggested solution

Monday, November 16, 2020

Question no 3761 : Other Goods Receipt Inspection

In SAP QM as at ECC6.0 EhP6, which of the following is the standard SAP Inspection Lot Origin for "Goods Receipt Others" ?

(only one answer)

A)  01.
B)  02.
C)  03.
D)  04.
E)  05.
.

click "1 comment" to view possible solution

Wednesday, November 11, 2020

Question no 3760 : Sampling Manual Entry

In SAP QM as at ECC6.0 EhP6, which of the following is the effects of setting "Manual Entry" for Sample Size in the Inspection Type detail in the Material Master ?

(only one answer)

A)  Sample Size is expected to be entered at MIGO screen.
B)  Sample Size is expected to be entered in the Purchase Order item detail.
C)  Sample Size is expected to be entered during Results Recording.
D)  Sample Size is expected to be entered in the Inspection Lot before it can be Released.
E)  Sample Size is expected to be entered in the Quality Info Record.
.

click "1 comment' to view suggested solution

Tuesday, November 10, 2020

Question no 3759 : Technical Types in BOM

In SAP PP as at ECC6.0 EhP6, "One product can be manufactured from alternative combinations of materials depending on the quantity to be produced (lot size). The product is represented by a number of alternative BOMs (alternatives). The differences between the alternative BOMs are only small. Usually the only difference is in the quantity of individual components. ", which Technical Type of this BOM is referring to ?

(only one answer)

A)  "A" Alternative.
B)  "C" Combinations.
C)  "T" Technical.
D)  "O" Option.
E)  "M" Multiple.
.

click "1 comment" to view suggested solution

Monday, November 9, 2020

Question no 3758 : Variant BOM

In SAP PP as at ECC6.0 EhP6, a Variant BOM has the following characteristics ?

(only one answer)

A)  The Header BOM can be different Materials.
B)  The Header BOM can be different Usages.
C)  The Header BOM can be different Plants.
D)  The Header BOM can be different Alternatives.
E)  The Header BOM can be different Plant and Alternatives.
.

Click "1 comment" for suggested solution

Wednesday, November 4, 2020

Question no 3757 : BOM

In SAP PP as at ECC6.0 EhP6, which of the following are TRUE about PP BOM ?

(more than one answers)

A)  When a BOM is first created, an alternative is not created.
B)  When a BOM is first created, it is automatically created as alternative 1.
C)  When a BOM is first created, the Technical Type is blank.
D)  When a BOM is first created, the Technical Type is "Standard".
E)  When a BOM is first created, it need not be created with a Plant.
.

clcik "1 commen" to view suggested solution

Tuesday, November 3, 2020

Question no 3756 : PP Bill of Material

In SAP PP as at ECC6.0 EhP6, which of the following are TRUE about Bill of Material ?

(more than one answers)

A)  A BOM can be assigned to one or more Plants.
B)  A BOM can be created and saved without a Plant.
C)  A Material as a BOM Header can be created with more than one BOM with different Usages.
D)  A Material as a BOM Header can be created with more than one BOM with different Alternatives.
E)  A BOM is always created with an Internal BOM number in the Header.
.

click "1 comment" to view suggested solution

Monday, November 2, 2020

Question no 3755 : Plant Maintenance Features

In SAP PM as at ECC6.0 EhP6, which of the following are TRUE describing Plant Maintenance Features ?

(more than one answers)

A)  There is no Plant Maintenance data view in the Material Master.
B)  Both FL and EQ can be assigned to a Material BOM via a Construction Type.
C)  Both FL and EQ can be linked to a Material-Serial.
D)  Both FL and EQ can be assigned to one or more Permit Masters.
E)  Both FL and EQ can be assigned with Measuring Points.
.

click "1 comment" for suggested solution