Question no 3658 : Item Category "R"
In SAP PP as at ECC6.0 EhP6, which of the following is the SAP definition for Item Category "R" for the BOM item ?
(only one answer)
A) Item Category.
B) Reference Item.
C) Stock Item.
D) Variable Sized Item.
E) Non-Stock Item.
.
Answer: D
(only one answer)
A) Item Category.
B) Reference Item.
C) Stock Item.
D) Variable Sized Item.
E) Non-Stock Item.
.
Answer: D
Monday, August 26, 2019
Saturday, August 24, 2019
Thursday, August 22, 2019
Wednesday, August 21, 2019
Question no 3657 : Maintenance Plan for SES
In SAP PM as at ECC6.0 EhP6, which of the following are characteristics of the Service Procurement Maintenance Plan that calls an SES ?
(more than one answers)
A) Framework Purchase Order.
B) Service master.
C) Cost Center.
D) Settlement Maintenance Order.
E) General Ledger.
.
Answers: A, B, D, E
Except cost center.
(more than one answers)
A) Framework Purchase Order.
B) Service master.
C) Cost Center.
D) Settlement Maintenance Order.
E) General Ledger.
.
Answers: A, B, D, E
Except cost center.
Monday, August 19, 2019
Sunday, August 18, 2019
Saturday, August 17, 2019
Friday, August 16, 2019
Thursday, August 15, 2019
Wednesday, August 14, 2019
Question no 3656 : Maintenance Item
In SAP PM as at ECC6.0 EhP6, which of the following can have only one Maintenance Item ?
(only one answer)
A) Single-Cycle Plan when the calling object is a Maintenance Notification.
B) Single-Cycle Plan when the calling object is a Maintenance Order.
C) Single-Cycle Plan when the calling object is a Inspection Lot.
D) Single-Cycle Plan when the calling object is a Service Entry Sheet.
E) Single-Cycle Plan when the calling object is a Purchase Order.
.
Answer: D
(only one answer)
A) Single-Cycle Plan when the calling object is a Maintenance Notification.
B) Single-Cycle Plan when the calling object is a Maintenance Order.
C) Single-Cycle Plan when the calling object is a Inspection Lot.
D) Single-Cycle Plan when the calling object is a Service Entry Sheet.
E) Single-Cycle Plan when the calling object is a Purchase Order.
.
Answer: D
Monday, August 12, 2019
Saturday, August 10, 2019
Thursday, August 8, 2019
Wednesday, August 7, 2019
Question no 3655 : Strategy Plan
In SAP PM as at ECC6.0 EhP6, which of the following are the characteristics of a Maintenance Plan ?
(more than one answers)
A) It can only have one unit of measure for the Strategy.
B) It can be either time or performance based.
C) The Maintenance Plan can have one or more Maintenance Items.
D) All Task List assigned to the maintenance Plan of a Strategy Plan must have the same Strategy.
E) Both EQ and FL are possible for Strategy Plans.
.
Answers: A, B, C, D, E
All of the above.
(more than one answers)
A) It can only have one unit of measure for the Strategy.
B) It can be either time or performance based.
C) The Maintenance Plan can have one or more Maintenance Items.
D) All Task List assigned to the maintenance Plan of a Strategy Plan must have the same Strategy.
E) Both EQ and FL are possible for Strategy Plans.
.
Answers: A, B, C, D, E
All of the above.