Question no 3667 : MRP for PP
In SAP PP as at ECC6.0 EhP6, which of the following is the setting for MRP run when the system first looks for a Routing, if Routing was not found, it will then revert to check either the Lot Size dependent data or Lot Size independent data in the Material Master ?
(only one answer)
A) Basic date scheduling.
B) Detail date scheduling.
C) Routing date scheduling.
D) 3 stage date scheduling.
E) Lead time scheduling.
.
Answer: E
Lead time scheduling.
(only one answer)
A) Basic date scheduling.
B) Detail date scheduling.
C) Routing date scheduling.
D) 3 stage date scheduling.
E) Lead time scheduling.
.
Answer: E
Lead time scheduling.
Tuesday, October 29, 2019
Monday, October 28, 2019
Saturday, October 26, 2019
Thursday, October 24, 2019
Wednesday, October 23, 2019
Question no 3666 : Enterprise Structure in MM
In SAP MM as at ECC6.0 EhP7, which of the following in not assigned to the Enterprise Structure ?
(only one answer)
A) Plant.
B) Storage Location.
C) Purchasing Organization.
D) Purchasing Group.
E) Company Code.
.
Click "1 comment" to view suggested answers
(only one answer)
A) Plant.
B) Storage Location.
C) Purchasing Organization.
D) Purchasing Group.
E) Company Code.
.
Click "1 comment" to view suggested answers
Monday, October 21, 2019
Saturday, October 19, 2019
Thursday, October 17, 2019
Wednesday, October 16, 2019
Question no 3665 : External Services
In SAP MM as at ECC6.0 EhP6, which of the following can use External Services with Service Masters ?
(more than one answers)
A) Production Order.
B) Maintenance Order.
C) Service Order.
D) Network Order.
E) Purchase Order.
.
click the "1 comment" to show suggested answers
(more than one answers)
A) Production Order.
B) Maintenance Order.
C) Service Order.
D) Network Order.
E) Purchase Order.
.
click the "1 comment" to show suggested answers
Monday, October 14, 2019
Saturday, October 12, 2019
Thursday, October 10, 2019
Wednesday, October 9, 2019
Question no 3664 : Maintenance Notification
In SAP PM as at ECC6.0 EhP6, which of the following is not true about a Maintenance Notification ?
(more than one answers)
A) It can be assigned to a PM Order to collect costs.
B) It can be generated via Saving a Maintenance Order.
C) It can be assigned with one or more General Task List.
D) It can be created without a reference Object.
E) It can be closed without converting to a Maintenance Order.
.
Click on "1 comment:" for suggested answer
(more than one answers)
A) It can be assigned to a PM Order to collect costs.
B) It can be generated via Saving a Maintenance Order.
C) It can be assigned with one or more General Task List.
D) It can be created without a reference Object.
E) It can be closed without converting to a Maintenance Order.
.
Click on "1 comment:" for suggested answer
Monday, October 7, 2019
Saturday, October 5, 2019
Thursday, October 3, 2019
Wednesday, October 2, 2019
Question no 3663 : Sampling Procedure with different Lot Sizes
In SAP QM as at ECC6.0 EhP6, to achieve sample size for different lot size ranges, which of the following is necessary ?
(only one answer)
A) Sampling Scheme.
B) Dynamic Modification.
C) Inspection Type activated in the IMG.
D) Inspection Lot Document Type activated in the IMG.
E) Material Specification.
.
Answer: A
(only one answer)
A) Sampling Scheme.
B) Dynamic Modification.
C) Inspection Type activated in the IMG.
D) Inspection Lot Document Type activated in the IMG.
E) Material Specification.
.