Question no 3639 : LIV reference document

In SAP MM as at ECC6.0 EhP6, which of the following possible reference documents for manual Logistics Invoice Verification ?

(more than one answers)

A)  Purchase Order.
B)  Material Document.
C)  Scheduling Agreement.
D)  Service Entry Sheet.
E)  Contract.
.

Answers: A, C, D

B) Material Document can be used for ERS but not manual LIV.
E) Contract cannot be subjected to GR, and it is not involved in LIV.