This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, March 15, 2015

Question no 2791 : PM posting to FI

In SAP PM as at ECC6.0 EhP6, which of the following processes do not result in any postings to Financial Accounting ?

(more than one answers)

A)   Activity confirmation.
B)   Overhead Calculation after Order TECO.
C)   Settlement of a Refurbishment Order.
D)   Backflushing of spare parts.
E)   Dismantle of Equipment.
.

4 comments:

  1. A, B) Both Activity Confirmation and Overhead calculation also debits costs to the Maintenance Order, there are no FI postings.

    ReplyDelete
  2. C) Standard SAP recommended process for Refurbishment is using Split Valuation material, and settlement receiver is the material. Therefore, settlements of refurb orders can result in FI posting regardless of material is 'V' or 'S' pricing control.

    ReplyDelete
  3. D) Backflushing is an Auto Goods Issue process done at Activity Confirmation and it will result in FI posting as along as the material is with value.

    ReplyDelete
  4. E) Equipment dismantling is a PM process and not necessary result in goods movement.

    ReplyDelete

Note: Only a member of this blog may post a comment.