Question no 2782 : MRP1, 2

In SAP MRP as at ECC6.0 EhP6, which of the following is not a mandatory field in the MRP view in the Material Master ?

(more than one answers).

A)  MRP Group.
B)  MRP Controller.
C)  MRP Type.
D)  Procurement Type.
E)  Special Procurement Key.
.

3 comments:

  1. E) Procurmnt type is mandatory to determine if it js internal or external procurement however special procurement key is optional.