Question no 2726 : Without Sampling Procedure

In SAP QM ECC6.0 EhP6, when performing a goods receipt with reference to a Purchase Order, the system cannot find a valid Sampling Procedure when crearing the Inspection Lot, what happens next (assuming a valid Inspection Plan was found) ? 

(only one answer) 

A)  The system abandons the Goods Receipt process. 
B)  Goods Receipt will be completed but the Inspection Lot is not created.
C)  An Inspection is created with a 'BLK' (Block) system status. 
D)  The system promots the receing clerk to enter a sample size in the MIGO screen.
E)  An Inspection Lot is creates with a 'CRTD' (Created) system status.
.


1 comment:

  1. Since a Valid inspection lot is found, the system would likely proceed to generate an Inspection Lot; however, no samples can be determined so the inspection lot is created qith Created System Status.