In SAP QM as at ECC6.0, EhP6, which of the following are possible activities when performing a Usage Decision ?
(more than one answer)
A) Record defects.
B) Generate a Return Purchase Order.
C) Activate quality notifications.
D) Confirm activities for QM orders.
E) Make stock postings.
.
(more than one answer)
A) Record defects.
B) Generate a Return Purchase Order.
C) Activate quality notifications.
D) Confirm activities for QM orders.
E) Make stock postings.
.
So far as I understand as at ECC6.0 EhP6, a Return Purchase Order (a PO with a 'Return' indicator in the PO line item, a movement type '161' will be executed at GR of the PO for the return process) cannot be generated at UD process point.
ReplyDelete