In SAP QM ECC6.0 EhP6, take note of the 'Ordered Quantity' field in the Quality Info Record, when it is updated ?
(more than one answers)
A) Saving a purchase requisition with a Quantity of 100 will not update the 'Ordered Quantity'.
B) Saving a purchase order with a Quantity of 100 will update the 'Ordered Quantity'.
B) Saving a contract with a Quantity of 100 will not update the 'Ordered Quantity'.
B) Saving a RFQ with a Quantity of 100 will not update the 'Ordered Quantity'.
B) Saving a delivery schedule for a scheduling agreement with a Quantity of 100 will update the 'Ordered Quantity'.
.
(more than one answers)
A) Saving a purchase requisition with a Quantity of 100 will not update the 'Ordered Quantity'.
B) Saving a purchase order with a Quantity of 100 will update the 'Ordered Quantity'.
B) Saving a contract with a Quantity of 100 will not update the 'Ordered Quantity'.
B) Saving a RFQ with a Quantity of 100 will not update the 'Ordered Quantity'.
B) Saving a delivery schedule for a scheduling agreement with a Quantity of 100 will update the 'Ordered Quantity'.
.
Answer: A, B, C, D, E