This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Thursday, January 10, 2013

Question no 1787 : Sampling Procedure requirement

In SAP QM ECC6.0, the requirement of entry of Sampling Procedure for the Master Inspection Characteristics in the Inspection Plan is determined by which of the following ?

(only one answer)

A)   Inspection Plan profile.
B)   Quality Control Key assigned to the Inspection Plan Operation.
C)   Master Inspection Characteristics itself.
D)   Indicator in the Inspection Plan Header.
E)   Inspection Plan type used to create the Inspection Plan.
.

1 comment:

  1. When defining the Master Inspection Characteristics, the "Control Indicators" folder allow you to set the "Sampling Procedure" indicator to ensure the entry of a sampling procedure is necessary when the MIC is assigned into the operation of the Inspection Plan.

    ReplyDelete