In SAP QM ECC6.0, which of the following are NOT TRUE about Inspection type assignment in the Material Master ?
(more then one answers)
A) More then one Inspection types with the same origins can be assigned to a material master in the same plant.
B) Multiple inspection types can be assigned the material master but there must be different inspection origins.
C) New inspection types cannot be added to the QM view once a material master is first created.
D) Once an inspection type is activated in the QM view of the material, it should not be de-activated until all inspection lot and QI stocks are cleared.
E) Assignment of the sampling procedure in the inspection type in the material master is mandatory.
.
(more then one answers)
A) More then one Inspection types with the same origins can be assigned to a material master in the same plant.
B) Multiple inspection types can be assigned the material master but there must be different inspection origins.
C) New inspection types cannot be added to the QM view once a material master is first created.
D) Once an inspection type is activated in the QM view of the material, it should not be de-activated until all inspection lot and QI stocks are cleared.
E) Assignment of the sampling procedure in the inspection type in the material master is mandatory.
.
Answer: B, C, E