In SAP PP ECC6.0, the Strategy 50 ____________________ .

(more then one answers)

A)   Make-to-Stock Strategy.
B)   Make-to-Order Strategy.
C)   Considers Make-to-Order Sales Order.
D)   Considers Planned Independent Requirements.
E)   MRP run will take place for Planned Independent Requirements.
.

2 comments:

  1. Strategy 50 is classified as a MTO (Make-to-Order) Strategy, it has the following characteristics:
    . Considers Planned Independent Requirement at MRP run.
    . Planned Orders created for the FG cannot be converted to Production Order if the Planned Orders are Pegged to the Planned Independent Requirement from the MRP run.
    . However, if the Planned Orders are Pegged to Sales Orders, then they can be converted to MTO Production Orders.
    . BOM components can have "Individual" or "Collective" indicator to denote either they are managed as MTO or MTS.