In SAP PP&MM ECC6.0, MRP run can automatically generate which of the following ?
(more then one answers)
A) Purchase Requisition.
B) Purchase Order.
C) Contract.
D) Contract Release Order.
E) Delivery Schedule for Scheduling Agreement.
.
(more then one answers)
A) Purchase Requisition.
B) Purchase Order.
C) Contract.
D) Contract Release Order.
E) Delivery Schedule for Scheduling Agreement.
.
The MRP run can generate the following:
ReplyDelete. PR without Source
. PR with Vendor (via Source Determination)
. PR with Contract (via Source Determination)
. PR with Scheducling Agreement (via Source Determination)
. Delivery Schedule (against Scheduling Agreement)