Question no 1484 : Maintenance Strategy for Service Procurement

In SAP PM, the Maintenance Plan for Maintenance Strategy of Service Procurement requires which of the following data ?

(more then one answers)

A)    Framework Purchase Order.
B)    Service Contract.
C)    Settlement Maintenance Order.
D)    Group Notification.
E)    Service Master.
.

1 comment:

  1. Review SAP menu - Logistics - PM - Preventive Maintenance - Maintenance Planning - Maintenance Plan - Create - For Service Procurement ....
    You will find that this MP scenario to call service entry sheets is a Single Cycle Plan and you should be entering the following data:
    1. Framework Purchase Order
    2. G/L Account for expenses A/C to debit when the service entry sheet is approved
    3. Settlement Maintenance Order to collect costs of the approved service entry sheet
    4. Service Master

    ReplyDelete