In SAP PP, the Strategy Group ________________________________ .
(more the one answers)
A) be assigned to the material master at the MRP 3 view.
B) can contain a Main Strategy but no Sub Strategies.
C) can contain one or more Main Strategy and several Sub Strategies.
D) can be assigned to the MRP type.
E) can be assigned to the MRP group.
.
(more the one answers)
A) be assigned to the material master at the MRP 3 view.
B) can contain a Main Strategy but no Sub Strategies.
C) can contain one or more Main Strategy and several Sub Strategies.
D) can be assigned to the MRP type.
E) can be assigned to the MRP group.
.
Answer: A, B, E
ReplyDelete