In SAP MM, which of the following is true about Factory Calender configuration ?
(more then one answers)
A) Only one factory calender can be assigned to each Plant.
B) Only one factory calender can be assigned to each Storage Location.
C) A factory calender can be assigned to several Plants.
D) Each factory calender can only have one public holiday calender.
E) Holidays assigned to the holiday calender are time dependent.
,
Answer: A, C, D, E
ReplyDeleteYou should review the customizing of the factory calender in
ReplyDeleteIMG - Netweaver - General Settings - Factory Calendar (path may be different for SAP versions).