In SAP PP ECC6.0, choose a PP strategy that allows you to perform MRP run using Planned Independent Requirements in order to purchase the input materials but the finished goods is not allowed to be produced until the Sales Orders arrive.
(only one answer)
A) Strategy 10.
B) Strategy 20.
C) Strategy 30.
D) Strategy 40.
E) Strategy 50.
.
(only one answer)
A) Strategy 10.
B) Strategy 20.
C) Strategy 30.
D) Strategy 40.
E) Strategy 50.
.
Strategy 50 is a Make-to-Order Strategy devised to recognize Planned Independent Requirements so that MRP can be executed to plan for the components while the Finished Goods will be produced once the Sales Order arrives.