Question 66
In the SAP PS system, Work Breakdown Structure (WBS) can do which of the following?
(multiple answers)
A) Plan Costs and Revenue.B) Enter a Budget.
C) Assign a Material.
D) Assign a Milestone.
E) Plan Dates and enter Actual Dates.
Question 67
"Operating Indicator" are used to indicator if WBS can be have Plan Cost, Post Actual Cost, and Post Revenues; which of the following are valid "Operating Indicators" that can be assigned to a WBS Element in the SAP PS system?
(multiple answers)
A) Costing Element.B) Planning Element.
C) Account Assignment Element.
D) Revenue Element.
E) Billing Element.
Question 68
Which of the following Network Activities can generate a Purchase Requisition?
(multiple answers)
A) "Internal Processing" Network Activity.Question 69
Which of the PS Objects can be assigned to a WBS Element?
(multiple answers)
A) Network Activity.B) Subordinate WBS Element.
C) Milestone.
D) PS Text.
E) DMS Document.
Question 70
For "Internal Processing" Network Activities, a Work Center can be assigned with Work hours which can enable the following function and process capabilities?
(multiple answers)
A) Allow for Detail Scheduling.B) Enter Actual Duration of Work done.
C) Evaluate Capacity Load.
D) Workforce Planning.
E) Activity Confirmation.
Question 71
____________________ is a user-friendly tool within SAP's Project System (PS) module that allows for simplified, quantity- and characteristic-based cost planning on Work Breakdown Structure (WBS) elements. It enables users to create cost estimates using predefined models and templates, providing an intuitive data entry screen for preliminary costing of projects.
(multiple answers)
A) Unit Costing.C) Structured-oriented Planning.
D) Detailed planning of primary costs.
E) Detailed planning of activity input.
Question 72
Which of the following process steps can Debit Actual Costs to the Project Network?
(multiple answers)
A) Goods Receipt of Project Stocks.B) Overhead Costs Calculations.
C) Confirmation of work hours for Internal Activity.
D) Invoice entry for Purchase Order from External Activities.
E) Goods Issue of Components assigned to the Network Activities.