Question no 4004 : Calibration Plan characteristics

In SAP Plant Maintenance as at ECC6 EhP8, the Calibration scenario characteristics are which of the following ?

(more than one answers)

A. Use Inspection Plan assigned to Equipment Master.
B. A Maintenance Task List with Inspection Characteristics is expected.
C. The Call object from the Calibration Plan is an Inspection Lot.
D. When the Maintenance Order is called and later Released then the Inspection Lot will be created.
E. The Equipment concerned for Calibration must be linked to a Material-Serial.
.

Answer: B, D

A) Inspection Plans cannot be assigned to Equipment Masters or Functional Location in ECC6.
B) Maintenance Task list with Inspection Characteristics are expected and this can be FL Task List, EQ Task List or General Task List. 
C, D) The call object for a Calibration is the Maintenance Order where later when the Order is Released, then it will create the Inspection Lot Automatically.
E) Calibration done internally do not required the Equipment link to Material-Serial (not necessary), just the Equipment or Functional Location is acceptable.





Sunday, March 20, 2016

Question no 3109 : Calibration Task List

In SAP QM as at ECC6 EhP6, which of the following are mandatory setup in the Calibration Task List for the Calibration scenario for PM-QM integation ?

(only than one answer)

A)  Inspection Point in the header of the General Task List.
B)  Inspection Point in the Equipment Master.
C)  Inpsection Point in the Master Inspection Characteristics.
D)  Inspection Point in the Maintenance Plan.
E)  Inspection Point in the Operation detail where the Master Inspection Characteristics area assigned at.
.

Monday, August 18, 2014

Question no 2638 : PM Calibration Inspection Type

In SAP QM-PM integration, the standard Inspection Type '14' is assinged to _________________ for Equipment Calibration.

(only one answer)

A)   Mantenance Plant Parameter.
B)   Equipment Category.
C)   Planning Plant Parameter.
D)   Planning Plant and Order Type.
E)   Order Type.

Sunday, January 12, 2014

Question no 2255 : Results Recording for Maintenance Calibration

In SAP PM/CS ECC6.0, at the Calibration results entry using Result Recording QE51N, what are possible ?

(more then one answers)

A)    Change the Modification Factor of the Maintenance Plan.
B)    Set the Equipment Status.
C)    Enter confirmation hours for the operation.
D)    Change the Valuation suggest by the system.
E)    Close the Maintenance Order.
.

Monday, January 6, 2014

Question no 2249 : Master Inspection Characteristics for QM Calibration

In SAP PM/QM ECC6.0, when creating the Master Inspection Characteristic LINKING to the Class Characteristics, what is defaulted from the Class Characteristics to the Master Inspection Characteristics ?

(more then one answers)

A)     Unit of measure.
B)     Values.
C)     Description.
D)     Sampling Procedure.
E)     Qualitative and Quantitative flag.
.

Wednesday, February 9, 2011

Question no 961 : QM Calibration

In SAP QM, the application of Quality Management in the Calibration Processing requires that the Inspection results from QM to be updated directly to the Equipment's Measurement Point, how can this be possible ?

(only one answer)

A)      Assign the Inspection characteristics to the Measuring Point of the Equipment concerned.
B)      Assign the Inspection characteristics directly to the Equipment master concerned.
C)      Use the characteristic that is used to create the Measuring Point to also create the Inspection
          Characteristics.
D)      Ensure the measuring point is assigned to the Calibration Plan together with the Inspection
          Characteristics used for the Maintenance Task List.
E)       Make sure the class where the characteristics is assigned to exist in the Calibration Plan,
          Maintenance Plan, and the Equipment Master.
.