In SAP MM Consumption Based Planning, select the correct sequence of a CBP planning sequence ?
i)    Procurement.
ii)   Scheduling.
iii)  BOM Explosion.
iv)  MRP Procedure.
v)   Lot Sizing.
(only one answer)
A)    ii, i, iv, v, iii
B)    v, iv, i, ii
C)    iv, v, iii, ii, i 
D)    iv, v, i, ii
E)    iv, v, i, ii, iii
.