In SAP MM & PP, the Pre-requisites required for Plant level MRP run in the Customizing is the following:
(more then one answers)
A) Activation of MRP at the Plant level.
B) Activation of MRP at the MRP area level.
C) Definition of the Plant Parameter.
D) Definition of the MRP Group Parameter.
E) Safety Stock control setup.
.
Answer: A, C
ReplyDelete