The Base quantity in the BOM header specifies:

(Select ONE best answer)

A)   which amount of the finished product the item quantities refer. 
B)   the basis of which MRP run will be executed. 
C)   which amount of scrap factor is applicable. 
D)   the multiplication factor for the item quantities.
E)    which amount of base line planning quantities needed for production. 