Question no : 316 PP Master Data Routing times

TERP10 (Unit 6) Manufacturing Execution

_________ is a lot-size independent time element and ___________ is a lot-size dependent time element within the definition of an operation in a Routing.

(Select ONE best answer)

A)   Independent time, Dependent time.
B)   Setup time, Variable time.
C)   Fixed time, Machine/Labour time. 
D)   Fixed time, Variable time. 
E)    Setup time, Machine/Labour time.