Question no : 299 PS Organization Concept

TERP10 (Unit 10) Project System 

The highest level of definition in a Project structure is the _________________ . 

(Select ONE best answer)

A)   Project definition. 
B)   Company code.
C)   WBS elements
D)   Client.
E)    Network graphics.