Question no : 298 PS Master Data Concept

TERP10 (Unit 10) Project System 

___________ is a model of a project, that shows the project activities to be fulfill in a hierarchical form. It also shows the operative basis for planning costs, revenues, and payments and also forms the basis for scheduling and budgeting.

(Select ONE best answer)

A)   Project definition. 
B)   Resources.
C)   WBS elements
D)   Activities.
E)    Network.