In SAP MM and PP, which of the following data elements is included in the process of calculating the MRP dates during the scheduling step of the MRP run ?
(more the one answer)
A) opening date.
B) goods receipt processing time.
C) goods issue processing time.
D) planned delivery time.
E) scheduling margin key.
.
(more the one answer)
A) opening date.
B) goods receipt processing time.
C) goods issue processing time.
D) planned delivery time.
E) scheduling margin key.
.
Answer: A, B, D