Question no 1111 : MRP Elements

In SAP MM and PP, which of the following are valid MRP Elements that will be published in the S/R List ?

(more the one answers)

A)    Contract.
B)    Delivery Schedule against the Scheduling Agreement.
C)    MRP generated Purchase Requisitons.
D)    Manually generated Purchase Requisitions.
E)    Reservations.
.